The Power Distribution Service (PDS) has been advised to shed load at various Bulk Supply Points to ensure system stability in Ghana’s power distribution.

Read Also: Minister charges new managers of ECG to work towards KPIs or get kicked out

A request by Ghana Grid Company Limited (GRIDCo) disclosed in a press release today said due to the construction of the road interchange at the ACP Junction, Pokuase, the capacity of the transmission network will be limited.

The statement signed by GRIDCo’s Head of Public Relations, Albert Kwasi Quainoo added that the construction has taken out of service the 330kV Aboadze-Tema transmission line traversing the road to enable the contractor to divert the power line.

Read Also: PDS takes over from ECG as the Electricity Service Provider Effective 1st March 2019

GRIDCo anticipates that the construction works would be completed by Tuesday, March 19, 2019.

“GRIDCo has accordingly advised Power Distribution Services (PDS) to redistribute loads at various Bulk Supply Points to ensure system stability. This may result in outages to some electricity consumers,” the statement said.

“It is anticipated that the diversion works would be completed by Tuesday, March 19, 2019”.